Update on Dallas North Tollway and Bush Turnpike improvements

Update on Dallas North Tollway and Bush Turnpike improvements

 Week of June 13

PRESIDENT GEORGE BUSH TURNPIKE: DNT TO U.S. 75

Current Construction

– Final grading underway and clean up between Coit Road and DNT

– Asphalt placement between Coit & Renner Roads

Potential Traffic Impacts

– Single lane closures will occur sporadically to allow for trucks to enter and exit construction area

– Construction area is primarily in the median between the east- and westbound main lanes

DALLAS NORTH TOLLWAY: PGBT TO I-635

Current Construction

– Installation of lighting conduit ongoing near I-635

– Drainage and fence removal underway between Trinity Mills Road and Keller Springs Road

Potential Traffic Impacts

– No construction will be scheduled on the DNT main lanes or ramps between 5 a.m. and 10 p.m. during the week, however, short-term exceptions may be made

– The speed limit, in this area, is now 60 MPH between the PGBT and Frankford Road and 55 MPH between Frankford and Belt Line Roads

DALLAS NORTH TOLLWAY: PGBT TO THE SAM RAYBURN TOLLWAY

Current Construction

– Continuing retaining wall work from PGBT to SRT

– Continuing construction of columns and caps for bridges from PGBT to SRT

– Bridge deck construction between Park Boulevard and Spring Creek Parkway

– Relocation of utility lines is ongoing

– Nightly June 14-23: Beams to be set for the expansion of the DNT/PGBT direct-connectors on the north side of the interchange

June 17-20:

– Beams to be set for the rebuilding of the northern portion of the Tennyson Parkway bridge

– The PGBT to northbound DNT direct-connector will be closed in order for crews to move concrete barriers to prepare for next phase of work

Potential Traffic Impacts

– Various lanes on Dallas Parkway (DNT frontage road)

– U-turn closures expected throughout construction

– Lane closures at the intersections at Tennyson Parkway and Dallas Parkway (DNT frontage road)

– No construction will be scheduled on the DNT main lanes or ramps between 5 a.m. and 8 p.m. during the week, however, short-term exceptions may be made

See a daily listing of scheduled lane and ramp closures at www.ntta.org. For more information call (972) 628-3134 or email [email protected].